How to use modify date

image
So guys i have a config file there is 1 column name “Date”. I want to give +1 date every run. Its like when i run today the config file is 18.11.2022, after that run i want to change the date in config file to be 19.11.2022 so tommorow the automation will give input from config file 19.11.2022

I dont really understand how to use modify activity because someone told me to use this but the feature is different


This screenshoot not mine, someone give it to me. Its so different with mine

HI,

For now, can you try to upgrade System.Activities package to 22.4.5 or 22.10.3? Issue of activities’ display might solve.

Regards,

Hi @Yoichi thanks for the answer, ill try

It works, thanks man @Yoichi