I couldn’t see any usage of SAP calendar in none of the process mining SAP app templates… This is a pity because this calendar is used for many SAP actions, and, for instance, would include the days a factory is closed.
This is especially strange when some working days metrics are explained in the documentation - using some csv.file, but interest of SAP calendar is that it’s per plant. See Process Mining - Custom throughput time metrics
Hey Olivier,
Thanks for sharing the above!
We are working on making it easier to calculate work times in general. But we hadn’t yet included adding the SAP calendar to the app templates on the roadmap. We’ll consider that as an improvement.
Thanks!