How to schedule one job after another

Hi team,

I have 3 process for a project to run on same bot.

First process: Need to run on every 3rd Wednesday of every month.
Second process: Need to run 15 days after First Process run.
Third process: Run daily.

Could you please help me in this for scheduling the first and second process…?

@jishnu.pnair

Welcome to our UIPath Community.

Use below cron expression. would trigger at 5:00pm on the Third Wednesday of every month.

                          0 0 17 ? * 4#3

I guess we don’t have any option to do this. You need to find the 3rd wednesday of the month and then add 15 days to it.

1 Like

Thanks bro

1 Like

Can we write a corn expression for second process also

@jishnu.pnair

We can’t. You need to manually add schedule dates in calendar and run it.

This topic was automatically closed 3 days after the last reply. New replies are no longer allowed.