Excel does not save after remote execution

I have built a process which writes some values in a excel file. I executed it in local with Studio and it worked perfectly. Then I have run from UI Path Platform and all the activities have executed sucessfully but, at the end the changes have not saved in the excel.

It is strange because, the excel activities were executed too.

Can anybody help me? Thank you

Hi, welcome to the community!
Please note that if you use a project relative path for your excel file, then you will need to go get it from the server to see it saved… most likely you will want to use a full file path there, like c:\myfolder\project\excelFile.xlsx

4 Likes

Thank you so much! This was exactly the problem I had :wink:

1 Like