# Estimating Dev time?

**URL:** <https://forum.uipath.com/t/estimating-dev-time/5777104>\
**Category:** Studio\
**Tags:** question, microsoft-office365, sap, activities\
**Created:** [September 15, 2026, 1:13pm UTC](https://forum.uipath.com/t/estimating-dev-time/5777104 "2026-09-15T13:13:50Z")\
**Posts on this page:** 8\
**Page:** 1

<div class="post-metadata">

**Author:** ![adext](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/adext/32/512643_2.png) [@adext](https://forum.uipath.com/u/adext)\
**Post date:** [September 15, 2026, 1:13pm UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/1 "2026-09-15T13:13:50Z")

</div>

Hello all,

I was wondering on which basis you usually estimate total days needed for a dev

For example, how would you proceed to estimate days needed for two SAP extractions (2 screens for each only - regular transaction details and csv download) and upload on Sharepoint?

I know it depends on the number of clicks etc but I am interested in the macro idea

Thanks a lot

---

<div class="post-metadata">

**Author:** ![Jasmin\_Bar](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/jasmin_bar/32/498877_2.png) [@Jasmin\_Bar](https://forum.uipath.com/u/Jasmin_Bar)\
**Post date:** [September 15, 2026, 1:24pm UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/2 "2026-09-15T13:24:02Z")

</div>

Hi @adext ,

For effort estimation, I usually break the automation into major components rather than counting every click:

- **Application analysis & access setup** (SAP, SharePoint, credentials)
- **SAP extraction development** (navigation, data extraction, CSV download)
- **SharePoint upload implementation**
- **Exception handling & logging**
- **Testing/UAT support**
- **Deployment & documentation**

For your example of **2 SAP transactions/screens with CSV downloads and SharePoint upload** , assuming the process is straightforward and selectors are stable, I would estimate roughly:

- Development: **1.5 to 3 days**
- Testing & bug fixes: **0.5 to 1 day**
- Documentation & deployment: **0.5 day**

**Total estimate: around 2.5 to 4.5 days.**

As a rule of thumb, estimate based on **complexity, number of applications involved, exception scenarios, and data volume** , then add a small buffer (15-25%) for unexpected issues. This usually gives a more realistic estimate than counting clicks alone.

Thanks

---

<div class="post-metadata">

**Author:** ![Anurita\_Mishra](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/anurita_mishra/32/550302_2.png) [@Anurita\_Mishra](https://forum.uipath.com/u/Anurita_Mishra)\
**Post date:** [September 15, 2026, 1:55pm UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/3 "2026-09-15T13:55:33Z")

</div>

For a rough estimate, I would not base the effort only on the number of clicks. I would estimate by application, transaction, integration, exception handling, and testing effort.

For the example described two SAP extractions, two screens per extraction, regular transaction details plus CSV download, followed by a SharePoint upload reasonable initial estimate would be:

 ![image](https://global.discourse-cdn.com/uipath/original/4X/4/9/9/4996205372ba1bd6aeb6860023b1e2b0e4008066.png)

---

<div class="post-metadata">

**Author:** ![vhvinodsai](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/vhvinodsai/32/552071_2.png) [@vhvinodsai](https://forum.uipath.com/u/vhvinodsai)\
**Post date:** [September 15, 2026, 5:32pm UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/4 "2026-09-15T17:32:37Z")

</div>

Hi @adext

Thanks for bringing up this in forum,

For the example in the screenshot — 2 SAP extractions (2 screens each), CSV download, then upload to SharePoint — I wouldn’t estimate purely by number of clicks. Estimate by workflow complexity + reusable components + exception handling + testing.  
For a reasonably experienced UiPath developer, I’d initially estimate around 5–7 working days:  
Work  
Estimate  
Process understanding + PDD/technical analysis  
0.5 day  
SAP login/navigation reusable component  
0.5 day  
SAP Extraction 1  
0.75 day  
SAP Extraction 2  
0.75 day  
CSV validation/file handling  
0.5 day  
SharePoint upload  
0.5 day  
Business + system exception handling, logging  
0.75 day  
Unit/integration testing  
0.75 day  
Fixes + buffer  
1 day  
Total  
~6 days  
If you’re giving an estimate to a manager/client before seeing the SAP screens, I’d say 5–7 developer days, subject to SAP/SharePoint access and application stability.  
For a production-grade UiPath solution, I would also separately account for UAT, deployment, documentation and hypercare. That can make the complete delivery timeline closer to 8–10 working days, even though actual development is ~5–7 days.

Let me know if this works for you and hit the solution if you like my estimation data.

Thanks & cheers!

---

<div class="post-metadata">

**Author:** ![ashokkarale](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/ashokkarale/32/474400_2.png) [@ashokkarale](https://forum.uipath.com/u/ashokkarale)\
**Post date:** [September 16, 2026, 3:52am UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/5 "2026-09-16T03:52:23Z")

</div>

@adext

The dev estimation is tricky thing to be perfect at first time.

You will have to consider your developer’s skills and experience as well while estimating. For example - For junior it would be 6 hours for senior it would be 3 hours and so on.

Make sure you are allocating minimum 20% additional buffer time on top of total estimation for all unforseen blockers and delayed.

---

<div class="post-metadata">

**Author:** ![Jon\_Smith](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/jon_smith/32/523286_2.png) [@Jon\_Smith](https://forum.uipath.com/u/Jon_Smith)\
**Post date:** [September 16, 2026, 4:01am UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/6 "2026-09-16T04:01:22Z")

</div>

Worth adding, this is something that is in high flux right now. Coding agents are dramatically changing where the effort might be.

On very simple processes like this the time savings might not be crazy vs manual stuff, but on longer ones, where the estimation also gets harder, the variance there can be high.

Estimates have always been hard.

---

<div class="post-metadata">

**Author:** ![Monali\_Vekariya](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/monali_vekariya/32/264397_2.png) [@Monali\_Vekariya](https://forum.uipath.com/u/Monali_Vekariya)\
**Post date:** [September 16, 2026, 2:18pm UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/7 "2026-09-16T14:18:53Z")

</div>

Hi @adext

I usually estimate based on the **complexity and number of steps** , not just clicks.

For example:

- SAP extraction 1 → development + testing
- SAP extraction 2 → development + testing
- SharePoint upload → development + testing
- Exception handling, logging and deployment
- Add some buffer for unexpected issues

For your example, I would first do a quick feasibility check, then estimate each component separately and add a small buffer.

The main factors are **SAP complexity, data volume, exception handling, reusability, and testing effort**.

---

<div class="post-metadata">

**Author:** ![iampnkz](https://sea2.discourse-cdn.com/uipath/user_avatar/forum.uipath.com/iampnkz/32/563573_2.png) [@iampnkz](https://forum.uipath.com/u/iampnkz)\
**Post date:** [September 16, 2026, 3:57pm UTC](https://forum.uipath.com/t/estimating-dev-time/5777104/8 "2026-09-16T15:57:07Z")

</div>

Hi @adext,

I would recommend starting with the Automation Business Analysis Fundamentals training. It will give you a basic idea of how to plan and estimate automation efforts.

> **[Automation Business Analysis fundamentals (v2024.10) Course | UiPath Academy](https://academy.uipath.com/courses/automation-business-analysis-fundamentals-v2024-10)**
>
> Automation Business Analysis fundamentals (v2024.10)

Once you work on a few automations, you will get better at estimating the effort based on your experience. The same automation can take 5 days for one developer and 3 days for another, depending on their experience.

Thanks!